Terminating a Construction Contract in Kuwait: Contractor Default, Notices and Claims

Portrait of Dr. Mansour Mohammed Al-Otaibi
Editorial responsibility and legal reviewer

Dr. Mansour Mohammed Al-Otaibi

Doctorate in Public International Law

Draft prepared for the firm’s legal editorial library using the linked official sources. Attribution of personal authorship or completed professional review requires approval from the named lawyer.

Published
Last editorial update
Approved legal review date
Not yet recorded

Legal editorial standards and correction requests →

When a contractor stops working or a project is being built contrary to the agreed specifications, the employer may be tempted to terminate immediately and appoint a replacement. Conversely, a contractor may contend that the employer withheld an essential drawing, failed to provide site access or refused payment for work already approved. Terminating a construction contract in Kuwait requires a disciplined review of the actual obligations, technical events and procedural steps. Kuwait Civil Code, Decree-Law No. 67 of 1980, regulates contracts for work, defective performance, delay and acceptance. This guide explains how the employer or contractor can build an evidence-based legal file before seeking termination, compensation or completion of the works through someone else. No single outcome or remedy follows automatically from a delay or an allegation of poor workmanship.

1. Contractor abandonment is not identical to a project delay

A work stoppage can be documented, but its meaning depends on its causes. The contractor may have removed all labour without explanation, or may have temporarily paused work awaiting revised engineering drawings, an approval or site access. Some financial disputes concern genuinely unpaid certified milestones; others involve a contested valuation or a defect-related retention. Counsel needs to identify which party undertook each obligation and what document establishes that undertaking.

A missed calendar date does not automatically prove a breach justifying termination. The review should begin with the actual date of access to a workable site, relevant permits, drawing approval, agreed programme, approved variations, extensions and instructions from the employer or consultant. Events outside one party’s control may overlap with delays attributable to that same party. These issues should be separated in a contemporaneous chronology rather than attributed broadly to “the contractor’s delay.”

2. Notice to correct defective performance: Article 667

Article 667 addresses defective or non-conforming performance while the works are in progress. Its first paragraph permits the employer to notify the contractor to correct the manner of performance within a reasonable period. If the period expires without appropriate correction, the employer may seek termination or authority for the works to be completed at the original contractor’s expense, if the nature of the work permits. The second paragraph provides for seeking termination without a notice period where remedying the defect or non-compliance is impossible. The third allows the court, in specified circumstances, to decline termination for a defect that does not substantially impair value or fitness for purpose, without necessarily eliminating a valid compensation claim.

Effective notice should identify the precise operation and specification in dispute, the facts established, the corrective step required, the reasonable time allowed and a means of proving delivery. An email demanding that an entire structure be rebuilt in a day may raise different questions from an engineer’s specific instruction to stop using a prohibited material. In all cases, the notice and its legal consequences must be read with the contract and applicable statutory requirements; a label such as “final warning” does not, by itself, give a message legal effect.

3. Serious delay before completion: Article 668

Article 668 addresses situations where the contractor is so delayed in starting or completing the works that proper completion within the contractual period is no longer realistically expected, or where the contractor’s conduct indicates an intention not to perform or renders performance impossible. The provision may permit the employer to seek termination without waiting for the contractual delivery date. This does not make every temporary shortage of workers equivalent to abandonment or every missed interim milestone an irremediable breach.

For a credible case, prepare a progress schedule identifying the original programme, changes, percentage of completed work, remaining critical activities, likely achievable completion dates, and which side could remove each obstacle. Photographs should be linked to verified dates and physical locations. Expert assessment may be useful when parties disagree about whether completion was realistically possible. Compensation and liquidated-damages calculations should be distinguished from the statutory basis for termination itself.

4. What if the employer prevents performance? Article 671

The law also protects contractors. Article 671 addresses a situation where the employer must carry out an act necessary for the contractor to perform but fails to do so at the proper time. The contractor may require performance within a reasonable time; if the employer does not comply, an application to terminate may be available, without prejudice to compensation where its conditions are met. Such cases may concern late site possession, materials supplied by the employer, design information or access necessary to continue the works.

That provision should not be oversimplified as a licence for a contractor to leave the site whenever there is a payment dispute. The contract may distinguish approved certificates, interim applications, retention and disputed variations. Each claim must be evaluated according to its conditions and evidence. Before suspending work, a contractor should consider its own notice obligations, the consequences of abandonment and whether there is a less prejudicial lawful response.

5. Why preserve the site’s condition before replacing the contractor?

When work appears defective or incomplete, an employer may need to remedy an urgent hazard or engage a new contractor. Yet significant changes to the site before reliable documentation may deprive both parties of evidence showing the extent of completed work, the nature of an alleged defect, material quantities and what a reasonable repair would cost. Counsel should assess the legally appropriate route for preservation of evidence, inspection or expert assessment where relevant.

Practical records include the latest approved drawings, site instructions, dated photographic documentation, inspection reports, testing results, access logs, material inventories and signed statements from those who can identify what they observed. Evidence must be obtained and preserved lawfully. In an immediate safety situation, urgent protective work should not be delayed merely for litigation strategy; instead document the risk, the indispensable measures, and the site condition before and after intervention as safely as possible.

6. Termination, refusal of acceptance and latent defects: different routes

Article 672 concerns the employer’s obligation to accept the work once complete and placed at its disposal, together with consequences of refusal without legitimate cause. Article 673 distinguishes a serious non-conformity rendering the work unfit for its intended purpose from less significant defects that may call for repair or a reduction in price under its conditions. Article 675 concerns the effect of acceptance on liability for visible and latent defects, subject to provisions including Article 692 governing special structural issues.

ProblemInitial legal provisionEvidence to preserveKey question
Defective execution during worksArticle 667Specifications, inspection and corrective noticeIs correction possible and was reasonable time given?
Delay preventing timely performanceArticle 668Programme, progress reports and causation evidenceDoes the delay satisfy the statutory test?
Employer prevents an essential actArticle 671Requests, refusal and site recordsWas the employer required and given a reasonable opportunity to act?
Dispute over handoverArticles 672–675Handover records and defect reservationsIs the defect obvious, hidden or sufficiently serious?
Structural safety concernSpecial provisions including Article 692Professional structural assessmentDoes the statutory building warranty apply?

A superficial decorating flaw should not be reclassified automatically as a serious structural defect. Equally, a dangerous failure of a load-bearing element should not be treated as an ordinary snagging item. The contract, technical findings and statutory building provisions have to be read together. See our Kuwait construction-disputes service for disputes involving certified payments, workmanship and handover.

7. Financial claims after a construction contract ends

In many matters there are at least three distinct financial issues: the amount earned for completed work, payments received or lawfully withheld, and compensation claimed for proven loss where the applicable conditions are met. The employer may claim reasonable completion or repair costs and delay losses, while the contractor may claim unpaid approved certificates, authorised variations or loss caused by an employer’s breach. These sums should not be combined in a single unsupported final figure.

Financial review normally examines the contract sum, measured work, valuation methods, variations, advances, retention, guarantees, invoices, bank transfers, credits, and the actual cost of reasonable replacement work. A contractual delay penalty is not necessarily payable merely because a date passed; its legal validity, allocation of delay and relevant statutory limitations require assessment. Similarly, an employer’s refusal to certify work is not conclusive proof that no payment could be due.

Where a debt is precisely established and meets the applicable statutory conditions, a payment-order procedure may be considered. But a complex dispute requiring engineering and accounting valuation cannot simply be forced into that route because the claimant requests money.

8. Documents owners and contractors should provide counsel

  1. The entire contract: signed agreements, specifications, drawings, schedules, amendments and agreed dispute-resolution procedures.
  2. Timeline: site possession records, commencement date, contract programme, amendments, extensions and interruptions.
  3. Site evidence: architect and engineer communications, progress photographs, meetings, inspection records and defect notices.
  4. Warnings and responses: original correspondence, evidence of delivery, corrective requests and the contractor’s explanation.
  5. Payment file: all applications, approved certificates, paid amounts, retentions, deductions, variations and guarantees.
  6. Replacement evidence: why another contractor was required, competitive quotations if available, invoices and the exact scope of remedial work.
  7. Technical material: professionally prepared engineering reports, testing and methodology, with sources and dates clearly stated.
  8. Forum documents: arbitration clause, jurisdiction agreement and any settlement or procedural communications.

Organising these materials can change the entire strategy. An apparent refusal to pay may really concern incomplete certification; a reported contractor delay may partly result from the employer’s late information; a claimed defect may be obvious at acceptance or only discoverable later. The appropriate claim follows the evidence rather than a generic template for terminating contracts.

9. Court proceedings, arbitration or negotiated completion?

The contract may prescribe a dispute notice, negotiation window or arbitration procedure before formal litigation. Where arbitration is invoked, Decree-Law No. 120 of 2026 must be considered for proceedings within its scope, including the transitional exclusion for arbitration already pending when the new law entered into force. Government-related works can raise additional approval or procurement issues. A lawyer should not assume that every privately drafted arbitration clause is valid and binding in every circumstance.

A carefully documented settlement may be suitable when a project can be finished without destroying the parties’ remaining commercial interests. It should clearly identify outstanding work, revised dates, interim payments, defect liability, records to be delivered and the effect of releasing claims. When the matter involves substantial non-performance or disputed technical facts, litigation or arbitration may be necessary. Refer to arbitration and dispute resolution, civil compensation, and contract review for the specific issues involved.

10. Illustrative case scenario: a delayed apartment project

An owner engages a contractor to deliver structural work and fit-out by an agreed date. The owner reports insufficient labour and falling progress. The contractor argues that the owner repeatedly changed the air-conditioning plans and refused to certify completed work. The owner appoints a replacement and seeks to charge the first contractor for the entire finishing programme.

A defensible assessment would distinguish original scope from extras, build a timeline of actual critical-path events, identify contractual responsibility for each delay and record the site’s condition before replacement. Not every cost invoiced by the second contractor necessarily belongs to the first contractor. Not every claim by the first contractor is automatically valid either. This example illustrates case analysis; it is hypothetical and is not represented as litigation handled by the firm.

Frequently asked questions

Can the employer terminate immediately when the contractor stops attending site?

Not automatically. The reason for the stoppage, seriousness, applicable contract and statutory grounds including Articles 667 and 668 should be reviewed.

Must the owner give a warning before terminating?

Article 667 sets a corrective-notice framework for defective performance, with a stated exception where remedy is impossible. Other grounds and contractual provisions must be analysed separately.

Can the contractor terminate when the owner fails to hand over the site?

Article 671 addresses an employer’s failure to do what is necessary for performance, subject to an appropriate request, reasonable period and the statutory conditions.

Does taking delivery waive every defect claim?

No categorical answer is safe. Obvious and hidden defects, acceptance records and special structural warranty provisions may have different legal effects.

Are liquidated delay damages payable regardless of causation?

No. The clause and any applicable limitations, cause of delay, employer contribution and evidential position must be examined.

Does appointing a replacement prove the first contractor’s liability?

No. The reason for replacement, procedural steps, proof of site condition, and scope and cost of substitute works must all be assessed.

Can a contractor recover payment for completed work after termination?

That depends on valuation, acceptance, payment triggers, termination grounds and any lawful deductions or counterclaims.

Legal source materials and official Kuwaiti references

When does a construction dispute call for professional legal review?

If a site has stopped operating, a notice of termination or replacement has been served, material defects have appeared or major payments remain contested, review the contract and evidence before actions that could materially change the site. You may request a consultation or explore our construction contract dispute services. Do not send confidential project files in an initial unsecured message.

General educational information under Kuwaiti law, not an official English translation or individual legal opinion. No representation, award, settlement or result is guaranteed. The governing agreement, law as amended and evidence may change the legal analysis.